ENKA - Tripoli SCPP 671 MW GT Installation
- Customer
- ENKA İnşaat ve Sanayi A.Ş. - ENKA Branch Office Tripoli
- Location
- Tripoli/Libya
- Start Date
- 19.04.2021
- Completion Date
- 31.10.2022
Project Description
The installation works for four sets of Siemens SGT5-PAC 2000E gas turbines, including the Air Intake, Piping Systems, Diffuser, T-Box, BOP (Balance of Plant), and Stack equipment, have been completed at the 671 MW Tripoli Simple Cycle Power Plant (SCPP), where the main employer is the Libya General Electricity Company (GECOL).
The gas turbines are dual-fuel type. The primary fuel will be light distillate oil (LDO), while the backup fuel will be natural gas, which is planned to be utilized in the future.